This is an old revision of the document!


Summer 2014 Plan

Schedule

May June July August Fall
0512192602091623300714212804111825————
System Alignment
1 Align optical setup
2 Calibrate acquisition procedure
3 Finalize reconstruction procedure
Live Cell Imaging
1 Perform live cell experiment comparison
2 High-content screening study
3 Journal article on HCS study
SPAD Array
1 SPAD array implementation and testing
Shipping / Logistics
1 Send streak camera to INO
2 Setup moved to Sunnybrook
System Improvements
1 Reference fiber length adjusted
2 2D-1D fiber array w/ better streak coupling
3 AR-coated galvo window scanners
Conferences
1 Orlando ECS Conference
2 Boston SBI2 Conference


January February March April Summer
0714212804111825041118250108152229————
Streak Camera Configuration
1Implement 2D-1D fiber array
2Characterize readout camera
3Implement readout camera in scan code
Reference Fiber Bundle
1Validate test bundle from Leonid
2Determine required length of patch cable
3Implement final reference bundle
4Incorporate drift correction into code
Galvo Scanner
1Test basic functionality
2Characterize beam shifting
3Implement driver and software controls
4Design sample scan code
5Implement into new optical setup
5Interface with experiment code
Beam Shaper (Spectral Applied Research)
1Design with circular core fiber
2Test the output through lenslet array
3Reproduce with square core fiber
4Implement into new optical system
Sample Imaging
1Image and reconstruct fixed sample
2Image and reconstruct live sample
Spectral System
1Replicate complete optical system
2Characterize fully improved system
3Perform test study
4Implement on Opera microscope at Sunnybrook

Navigation
Personal Tools