Main works in summer
Finish system .
May
5 / 4 - 5 / 10 :
Restart the cell culture and data analysis of (L1_1.5hr to 4 hr)
5 / 11 - 5 / 17 :
Data analysis (Cells are getting happier during these two weeks)
5 / 18 - 5 / 24 :
Start FLIM experiment using SP5
- Low concentration (5ug/ml), 1 hour of incubation (need 2 more replicates)
- Data analysis
5 / 25 - 5 / 31 :
FLIM experiment (cont'd)
- Low concentration (5ug/ml), 1.5 hr to 4 hr of incubation (need 2 more replicates)
- Data analysis
June
6 / 1 - 6 / 10:
FLIM experiment and organize all results (low concentration)
- Low concentration (5ug/ml), 18 hr of incubation – need 2 more replicates
- Data analysis
6 / 11 - 6 / 30:
Organize all results using low concentration Photofrin
- Decide what other measurements need to be done (i.e. calibration of IRF..etc) after summarizing the results.
- Note: We don't have any repetitive measurement for high concentration photofrin (20 ug/ml), not sure if it's necessary
July
7 / 1 - 7 / 30:
to be arranged based on experimental results and due date
- May start to finalize FLIM project, hopefully will be able to start the manuscript preparation (i.e. write-up of some results and methods). Angela may perform some leftover experiments.
August
Hopefully working on the manuscript of FLIM project. To be arranged based on the progress.